NFS 1852.236-73 — Hurricane plan

NFS — NASA · Contract clause · dated DEC 1988 · prescribed in 1836.570

Official text of 1852.236-73

As prescribed in 1836.570(c), insert the following clause:

Hurricane Plan (DEC 1988)

In the event of a hurricane warning, the Contractor shall—

(a) Inspect the area and place all materials possible in a protected location;

(b) Tie down, or identify and store, all outside equipment and materials;

(c) Clear all surrounding areas and roofs of buildings, or tie down loose material, equipment, debris, and any other objects that could otherwise be blown away or blown against existing buildings; and

(d) Ensure that temporary erosion controls are adequate.

(End of clause)

Where it's prescribed

As prescribed in 1836.570(c), insert the following clause:

Verifying this text

The text above is reproduced verbatim from GSA's published source files for the NASA supplement. The controlling version is the one in the Code of Federal Regulations: 1852.236-73 on eCFR.