Official text of 1852.232-79
As prescribed in 1832.111-70, insert the following clause:
Payment for On-Site Preparatory Costs (SEP 1987)
Costs associated with on-site preparatory work (start-up or set-up costs) will be prorated over all work activities of a Critical Path Method (CPM) network or Progress Chart against which progress payments will be sought. Separate payment for on-site preparatory costs will not be made by the Government.
(End of clause)