NFS 1852.216-85 — Estimated cost and award fee

NFS — NASA · Contract clause · dated SEP 1993 · prescribed in 1816.406-70

Official text of 1852.216-85

As prescribed in 1816.406-70(e), insert the following clause:

Estimated Cost and Award Fee (SEP 1993)

The estimated cost of this contract is $______. The maximum available award fee, excluding base fee, if any, is $______. The base fee is $______. Total estimated cost, base fee, and maximum award fee are $______.

(End of clause)

Alternate I (SEP 1993). As prescribed in 1816.405-70(e), insert the following sentence at the end of the clause:

The maximum positive performance incentive is $______. The maximum negative performance incentive is (1).

(1) For research development hardware contracts, insert [equal to total earned award fee (including any base fee)]. For production hardware contracts, insert [$total potential award fee amount, including any base fee)].

(End of clause)

Where it's prescribed

As prescribed in 1816.406-70(e), insert the following clause:

Verifying this text

The text above is reproduced verbatim from GSA's published source files for the NASA supplement. The controlling version is the one in the Code of Federal Regulations: 1852.216-85 on eCFR.