GSAM 552.246-72 — Final Inspection and Tests

GSAM — General Services Administration · Contract clause · dated Sep 1999 · prescribed in 546.312

Official text of 552.246-72

As prescribed in 546.312 , insert the following clause:

Final Inspection and Tests (Sep 1999)

The Contractor shall give written notice to the Contracting Officer at least 10calendar days before the date the work will be completed and ready for final inspection and tests. Final inspection and tests will begin within 10calendar days after the date specified in the Contractor’s notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

(End of clause)

Where it's prescribed

As prescribed in 546.312 , insert the following clause:

Verifying this text

The text above is reproduced verbatim from GSA's published source files for the General Services Administration supplement. The controlling version is the one in the Code of Federal Regulations: 552.246-72 on eCFR.