EPAAR 1552.217-73 — Option for increased quantity—cost-type contract

EPAAR — Environmental Protection Agency · Contract clause · dated JUN 1997 · prescribed in 1517.208

Official text of 1552.217-73

As prescribed in 1517.208(d), insert this contract clause in cost-reimbursement type term form contracts when applicable. If only one option period is used, enter “NA” in the proper places of the clause. If more than two option periods apply, modify the clause accordingly.

Option for Increased Quantity—Cost-Type Contract (JUN 1997)

(a) By issuing a contract modification, the Government may increase the estimated level of effort by ____ direct labor hours during the base period, ____ during the first option period, and ____ during the second option period. The Government may issue a maximum of ____ orders to increase the level of effort in blocks of ____ hours during any given period. The estimated cost and fixed fee of each block of hours is as follows:

Base period Option 1 Option 2
Estimated cost
Fixed fee
Total

(b) When these options are exercised, paragraph (a) of the “Level of Effort” clause and the “Estimated Cost and Fixed Fee” clause will be modified accordingly.

(c) If this contract contains “not to exceed amounts” for elements of other direct costs (ODCs), those amounts will be increased as follows:

Other direct cost item Option 1 Option 2

(End of clause)

Where it's prescribed

As prescribed in 1517.208(d), insert this contract clause in cost-reimbursement type term form contracts when applicable. If only one option period is used, enter “NA” in the proper places of the clause. If more than two option periods apply, modify the clause accordingly.

Verifying this text

The text above is reproduced verbatim from GSA's published source files for the Environmental Protection Agency supplement. The controlling version is the one in the Code of Federal Regulations: 1552.217-73 on eCFR.