DFARS 252.204-7002 — Payment for Contract Line or Subline Items Not Separately Priced

DFARS — Defense (DoD) · Contract clause · dated APR 2020 · prescribed in 204.7109

Official text of 252.204-7002

As prescribed in 204.7109 (a), use the following clause:

Payment for CONTRACT LINE OR Subline Items Not Separately Priced (APR 2020)

(a) If the schedule in this contract contains any contract line or subline items identified as not separately priced (NSP), it means that the unit price for the NSP line or subline item is included in the unit price of another, related line or subline item.

(b) The Contractor shall not invoice the Government for an item that includes in its price an NSP item until—

(1) The Contractor has also delivered the NSP item included in the price of the item being invoiced; and

(2) The Government has accepted the NSP item.

(c) This clause does not apply to technical data.

(End of clause)

Where it's prescribed

As prescribed in 204.7109 (a), use the following clause:

Statutory obligations this clause carries

Determined by what the clause text itself cites, not by its title.

The same obligation, other agencies

Other supplements imposing Rights in data and software.

Verifying this text

The text above is reproduced verbatim from GSA's published source files for the Defense (DoD) supplement. The controlling version is the one in the Code of Federal Regulations: 252.204-7002 on eCFR.