In plain English
FAR 52.247-35, F.o.b. Destination, Within Consignee’s Premises, is a contract clause prescribed at FAR 47.303-7(c), most recently dated Apr 1984. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.
Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.
Does it flow down to subcontracts?
No flowdown mandate found in the clause text
We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.
Where it's prescribed
As prescribed in 47.303-7(c), insert the following clause in solicitations and contracts when the delivery term is f.o.b. destination, within consignee’s premises:
Prescribing reference: FAR 47.303-7(c).
The official text, verbatim
As prescribed in 47.303-7(c), insert the following clause in solicitations and contracts when the delivery term is f.o.b. destination, within consignee’s premises:
F.o.b. Destination, Within Consignee’s Premises (Apr 1984)
-
(a) The term "f.o.b. destination, within consignee’s premises," as used in this clause, means free of expense to the Government delivered and laid down within the doors of the consignee’s premises, including delivery to specific rooms within a building if so specified.
-
(b) The Contractor shall-
-
(1)
-
(i) Pack and mark the shipment to comply with contract specifications; or
-
(ii) In the absence of specifications, prepare the shipment in conformance with carrier requirements;
-
-
(2) Prepare and distribute commercial bills of lading;
-
(3) Deliver the shipment in good order and condition to the point of delivery specified in the contract;
-
(4) Be responsible for any loss of and/or damage to the goods occurring before receipt of the shipment by the consignee at the delivery point specified in the contract;
-
(5) Furnish a delivery schedule and designate the mode of delivering carrier; and
-
(6) Pay and bear all charges to the specified point of delivery.
-
(End of clause)