FAR 52.247-28 — Contractor’s Invoices

Contract clause · dated Apr 1984 · prescribed in FAR 47.207-9(c) · current through FAC 2026-01

In plain English

FAR 52.247-28, Contractor’s Invoices, is a contract clause prescribed at FAR 47.207-9(c), most recently dated Apr 1984. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.

Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.

Does it flow down to subcontracts?

No flowdown mandate found in the clause text

We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.

Where it's prescribed

As prescribed in 47.207-9(c), insert the following clause in solicitations and contracts for drayage or other term con- tracts for transportation or for transportation-related services:

Prescribing reference: FAR 47.207-9(c).

The official text, verbatim

FAR 52.247-28 · Apr 1984 current through FAC 2026-01 acquisition.gov eCFR (48 CFR)

As prescribed in 47.207-9(c), insert the following clause in solicitations and contracts for drayage or other term con- tracts for transportation or for transportation-related services:

Contractor’s Invoices (Apr 1984)

The Contractor shall submit itemized invoices as instructed by the agency ordering services under this contract. The Contractor shall annotate each invoice with the contract number and other ordering office document identification.

(End of clause)

The text above is reproduced from GSA's published FAR source files (GSA/GSA-Acquisition-FAR @ da52ccb (2026-03-30)), retrieved 2026-07-17. The official publication at acquisition.gov / eCFR controls if they differ.