FAR 52.242-15 — Stop-Work Order

Contract clause · dated Aug 1989 · prescribed in FAR 42.130 · current through FAC 2026-01

In plain English

FAR 52.242-15, Stop-Work Order, is a contract clause prescribed at FAR 42.130, most recently dated Aug 1989. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.

Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.

Does it flow down to subcontracts?

No flowdown mandate found in the clause text

We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.

Where it's prescribed

As prescribed in 42.1305(b), insert the following clause. The "90-day" period stated in the clause may be reduced to less than 90 days.

Prescribing reference: FAR 42.130.

The official text, verbatim

FAR 52.242-15 · Aug 1989 current through FAC 2026-01 acquisition.gov eCFR (48 CFR)

As prescribed in 42.1305(b), insert the following clause. The "90-day" period stated in the clause may be reduced to less than 90 days.

Stop-Work Order (Aug 1989)

  • (a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either-

    • (1) Cancel the stop-work order; or

    • (2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.

  • (b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if-

    • (1) The stop-work order results in an increase in the time required for, or in the Contractor’s cost properly allocable to, the performance of any part of this contract; and

    • (2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim submitted at any time before final payment under this contract.

  • (c) If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement.

  • (d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.

(End of clause)

Alternate I (Apr 1984). If this clause is inserted in a cost-reimbursement contract, substitute in paragraph (a)(2) the words "the Termination clause of this contract" for the words "the Default, or the Termination for Convenience of the Government clause of this contract." In paragraph (b) substitute the words "an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected" for the words "an equitable adjustment in the delivery schedule or contract price, or both."