FAR 52.242-1, Notice of Intent to Disallow Costs, is a contract clause prescribed at FAR 42.802, most recently dated Apr 1984. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.
Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.
Does it flow down to subcontracts?
No flowdown mandate found in the clause text
We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.
Where it's prescribed
As prescribed in 42.802 , insert the following clause in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated:
Prescribing reference: FAR 42.802.
The official text, verbatim
As prescribed in 42.802 , insert the following clause in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated:
Notice of Intent to Disallow Costs (Apr 1984)
-
(a) Notwithstanding any other clause of this contract-
-
(1) The Contracting Officer may at any time issue to the Contractor a written notice of intent to disallow specified costs incurred or planned for incurrence under this contract that have been determined not to be allowable under the contract terms; and
-
(2) The Contractor may, after receiving a notice under paragraph (a)(1) of this clause, submit a written response to the Contracting Officer, with justification for allowance of the costs. If the Contractor does respond within 60 days, the Contracting Officer shall, within 60 days of receiving the response, either make a written withdrawal of the notice or issue a written decision.
-
-
(b) Failure to issue a notice under this Notice of Intent to Disallow Costs clause shall not affect the Government’s rights to take exception to incurred costs.
(End of clause)