FAR 52.237-3 — Continuity of Services

Contract clause · dated Jan 1991 · prescribed in FAR 37.110(c) · current through FAC 2026-01

In plain English

FAR 52.237-3, Continuity of Services, is a contract clause prescribed at FAR 37.110(c), most recently dated Jan 1991. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.

Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.

Does it flow down to subcontracts?

No flowdown mandate found in the clause text

We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.

Where it's prescribed

As prescribed in 37.110(c), insert the following clause:

Prescribing reference: FAR 37.110(c).

The official text, verbatim

FAR 52.237-3 · Jan 1991 current through FAC 2026-01 acquisition.gov eCFR (48 CFR)

As prescribed in 37.110(c), insert the following clause:

Continuity of Services (Jan 1991)

  • (a) The Contractor recognizes that the services under this contract are vital to the Government and must be continued without interruption and that, upon contract expiration, a successor, either the Government or another contractor, may continue them. The Contractor agrees to-

    • (1) Furnish phase-in training; and

    • (2) Exercise its best efforts and cooperation to effect an orderly and efficient transition to a successor.

  • (b) The Contractor shall, upon the Contracting Officer’s written notice, (1) furnish phase-in, phase-out services for up to 90 days after this contract expires and (2) negotiate in good faith a plan with a successor to determine the nature and extent of phase-in, phase-out services required. The plan shall specify a training program and a date for transferring responsibilities for each division of work described in the plan, and shall be subject to the Contracting Officer’s approval. The Contractor shall provide sufficient experienced personnel during the phase-in, phase-out period to ensure that the services called for by this contract are maintained at the required level of proficiency.

  • (c) The Contractor shall allow as many personnel as practicable to remain on the job to help the successor maintain the continuity and consistency of the services required by this contract. The Contractor also shall disclose necessary personnel records and allow the successor to conduct on-site interviews with these employees. If selected employees are agreeable to the change, the Contractor shall release them at a mutually agreeable date and negotiate transfer of their earned fringe benefits to the successor.

  • (d) The Contractor shall be reimbursed for all reasonable phase-in, phase-out costs (i.e., costs incurred within the agreed period after contract expiration that result from phase-in, phase-out operations) and a fee (profit) not to exceed a pro rata portion of the fee (profit) under this contract.

(End of clause)

The text above is reproduced from GSA's published FAR source files (GSA/GSA-Acquisition-FAR @ da52ccb (2026-03-30)), retrieved 2026-07-17. The official publication at acquisition.gov / eCFR controls if they differ.