FAR 52.236-2 — Differing Site Conditions

Contract clause · dated Apr 1984 · prescribed in FAR 36.502 · current through FAC 2026-01

In plain English

FAR 52.236-2, Differing Site Conditions, is a contract clause prescribed at FAR 36.502, most recently dated Apr 1984. The complete official text is reproduced below, verbatim, from GSA's published FAR source files.

Its text contains no sentence requiring insertion into subcontracts; see the flowdown section below for what that does and does not mean.

Does it flow down to subcontracts?

No flowdown mandate found in the clause text

We scanned the full clause text and found no sentence directing the contractor to insert this clause into subcontracts. That is a statement about the text, not legal advice: a prime contractor may still flow terms down contractually, an agency supplement (DFARS, VAAR, …) may add requirements, and clauses listed below (if any) may order this clause into subcontracts from the outside.

Where it's prescribed

As prescribed in 36.502 , insert the following clause:

Prescribing reference: FAR 36.502.

The official text, verbatim

FAR 52.236-2 · Apr 1984 current through FAC 2026-01 acquisition.gov eCFR (48 CFR)

As prescribed in 36.502 , insert the following clause:

Differing Site Conditions (Apr 1984)

  • (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of-

    • (1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract; or

    • (2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

  • (b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

  • (c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) of this clause for giving written notice may be extended by the Contracting Officer.

  • (d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

(End of clause)

The text above is reproduced from GSA's published FAR source files (GSA/GSA-Acquisition-FAR @ da52ccb (2026-03-30)), retrieved 2026-07-17. The official publication at acquisition.gov / eCFR controls if they differ.